MCC Update November 2026

2 November 2026

As the pace of construction keeps momentum and good progress is made, we remain on target for the completion of the new Mayfield Community and Health Centre for the end of May 2027.  

Most of September’s work was underground with the retaining walls, strip footings, drainage and service ducts and sub-structure blockwork finished at the northern end of the site for the health centre. During the month of October, however, similar underground works at the southern end for the community hall were well underway including the installation of drainage, footings and service ducts.

Also during October, the 120-ton mobile tower crane made a re-appearance on site having off-loaded and installed the pre-cast floor slabs for the health centre the previous month. Within two days it had off-loaded and installed the pre-cast floor slabs for the community centre. The crane was so high the top of the jib could be seen for miles around.

With the sub-structures for both the community hall and health centre complete, the above ground super-structure will be erected from early November. It is a pre-fabricated modular building whereby the component panels are manufactured off-site by a company called Streif UK Ltd and transported ready for on-site assembly. This form of construction enables the building to go up quickly, and, all being well, it will be completed by Christmas.

 In the New Year 2027, the external stone and brickwork will be added to provide the final external aesthetics of the building. 

A reminder about the purpose of the project

To develop a new purpose-built sustainably built Community and Health Centre for the Parish of Mayfield and Five Ashes in partnership with Wealden District Council for the benefit of its residents.

  • Main Benefits and Features:
  • A multi-purpose (23m x 10m) Community Hall
  • De-mountable stage to maximise flexibility of use of the Main Hall
  • Purpose built lower ground-floor health centre (350 m2) incorporating 4 no. GP Rooms, 3 No. Treatment Rooms, 21 Patient Waiting Room and ancillary Staff Spaces.
  • MAYFACS office
  • Community Hub
  • Meeting Rooms (2)
  • Car parking for 84 cars (50% larger than existing car park)
  • Enlarged two-way vehicular access with improved safety
  • Electric (vehicle) charging points
  • Terraced area with magnificent open views across Court Meadow
  • Preservation of existing tree line and open space
  • Occupying existing developed 2 acre site
  • Retention of existing band hut
  • Planned completion date - end 2023